Value: £1.1m

Size: 5420m2 (over 9 slabs)

Duration: 24 weeks

Rig: 13.5t. Midi & 35t. Piling Rigs

Scope of work:

  • Our project with Osborne involved the design and installation of our non-voided Comdeck system for multi-story buildings comprising of apartments and offices.

  • We installed a total of 1213No. 300mm diameter CFA piles, to an average of 7m deep, with a 13.5t midi piling rig and 240No. 250mm diameter CFA piles up to 23m deep with a 35t. piling rig.

  • We constructed 225mm and 300mm thick reinforced concrete Comdeck slabs incorporating the Abbey Pynford galvanised sacrificial straight shutter system.

  • Our design included a spanning system, incorporated within some of the proposed slabs, to bridge a Thames Water sewer of 2.4m diameter located 6m below ground level.

  • One of the benefits of using Comdeck on this site was the ability for Osborne to continue construction of adjacent slabs, reducing the programme.